natural gas transmission and Distribution Pipeline design ,constructionand operations expert
This is a candidate registered on Gulfoilandgas.com. To contact this candidate you need to purchase a subscription.
Education: 4
Experience: 20 years
Relocation: Yes - Internationally
Career Objective
Natural gas Pipeline Transmission/Distribution Design engineering
Professional Experience
Highly driven downstream gas industry professional engineer with 36 years experience including last 10 years at Corporate level. Successful track record in all activities including gas utilization, distribution system planning and design, cathodic protection, operations, customer service, gas dispatch, SCADA, distribution construction, transmission pipeline planning, simulation, and construction, gas measurement, HSE, domestic gas meter manufacturing and IT related work including front and back office system and development of GIS. Highly skilled in project planning & management, contract negotiations with multinational E&P organization and large customers (including IPP’s) such as power plants, integrated steel mills, fertilizer & chemical units. Excellent analytical and problem solving skills in business management with strong educational background in engineering and management.
Eductation
Post Graduate Diploma in Business Administration
University of Karachi – 1973
Bachelor of Science (Hons’) in Fuel Engineering
University of Leeds England - 1968
Pakistan Engineering Council
- NACE Course on Corrosion Protection by Cathodic Protection
- Corrosion Control Course by British Gas in UK
- Applied Financial Analysis, Practices and Strategies for Energy Sector
- Transition from Public to Private Sector
- Contract negotiation course by British Gas
- International Tendering by Asian Development Bank
Additional Information
Sr. General Manager Engineering Services Sui Southern Gas Company Ltd.Karachi Pakistan
Planning, design and construction of long distance Class 600 transmission pipeline system including measurement system, filtration etc. involved since year 2000.
The project named as “Gas Infrastructure Rehabilitation and Expansion Project (GIREP) was initiated in year 2000 and aimed to achieve the following by June 2004:
1) To integrate the new gas finds equal to 750 MMCFD with SSGC system through additions of 100 kms of transmission system in size ranging from 16 – 18”, 20” & 24”.
2) To optimize system capacity through simulation studies to transmit and distribute 1200MMCFD of Gas (increase from 500-1250 MMCFD).
3) Relocation of compressor stations.
4) Rehabilitation of 555 kms of 50 year old 16” transmission line
(replacement of 12” by 16” ball valve and installation of pig
launcher & receiver).
5) Total cost of project US$ 55 million.
6) Project successfully completed in June 2004 on schedule and without cost overrun.