(1) FROM 04thAPR 2005 TO TILL NOW: -
Organization Dodsal Pte Ltd.
Designation Planning Engineer
Client Dolphin Energy Limited
Main Contractor JGC ME FZE
Project Dolphin Onshore Gas Plant Project
(Sub-Contract : Mechanical and Painting Works ?V MC-2)
Location Ras Laffan Industrial City
Country Qatar; Middle East Asia
Duties & Responsibilities:
„I Project Time Management
1. Scheduling: Development of Base Line Schedule using Planning Software PRIMAVERA (P3).
2. Preparation of Weekly; Monthly & Three Months look-ahead Schedule. Updating actual Progress and all related information & comparison analysis.
„I Project Scope Management
1. Tracking and maintain scope changes of Mechanical items for Piping; Structural Steel; Piping & Mechanical Equipments and its effect on the overall project schedule.
„I Resource Management
1. Resources Estimation and Loading in P3 plan.
2. Estimation of Manpower Requirement for the Project based on standard productivity norms. Monitoring of actual resources availability & analysis using Histogram.
3. Budget Monitoring & estimation of CTC.
„I Project Communications Management
1. MIS: Preparing progress % calculation systems, earned man-hours, productivity & Trend analysis.
2. Progress Measurement using S Curves.
3. Preparation Executive Progress Summary Report / Presentations to the Top Management on Project Status for periodical review.
4. To interact with PCM & issue project MIS to Client & H.O. on daily; weekly & monthly basis.
(2) FROM 25th NOV 2002 TO 15th MAR 2005:-
Organization RELIANCE ENGINEERING ASSOCIATES PVT. LTD.
Agency Delta Technical Services
Designation Planning Engineer
Duties & Responsibilities:
1. Preparation of schedule in Primavera and monitoring of progress.
2. Review and forecast Contractor Work front availability and conduct continuity of work analysis.
3. Resource Planning: To work out detailed resource Requirement based on standard productivity norms.
4. Material & Resources Planning for Infocomm & Retail Outlet Project.
(3) FROM 01st JUL 2002 TO 23rd NOV 2002: -
Organization ARIO BROTHERS
Designation GET
Client IGL
Consultant EIL
Project 12?¨ Under Ground CNG Pipeline Project
Location North Delhi, India
Duties & Responsibilities:
1. Execution of 12?¨ UG CNG Gas Pipeline.
Eductation
Graduate Diploma in Construction Project Management (2004) with 54.33 % from National Institute of Const. Management & Research; PUNE
B. E. Mechanical (2002)with 68.05 % from Shri SVM Institute of Technology, South Gujarat University
Additional Information
Date of Birth : 10th September 1980.
Passport No. : E6270660 valid up to year 2013.
Language Known : English; Hindi & Gujarati.
Nationality : Indian.
Blood Group : B +
Marital Status : Unmarried.
Hot Categories
Chemicals
Batteries