PROJECT HIGHLIGHTS :
ľ Hawiyah NGL Recovery Project (Saudi Armco- KSA (Main contractor JGC Japan)
ƒæ Sohar Refinery Project ¡V Oman (Main contractor JGC Japan)
ƒæ Oman India Fertilizer Project ¡V Oman (JV Technip France)
ƒæ 500 MW Atomic power Project Primary Piping ¡VNPCIL ¡VTarpur ¡VBombay.
ľ Reliance Petroleum Ltd Jamnagar.
ľ Reliance Petro Chemicals Ltd Hazira.
ľ Mangalore refinery & Petro Chemicals ltd.
ľ Rastria chemicals & Fertilizers Ltd Trombay.
ľ Chambal fertilizers and chemicals ltd Kota.
ľ Oriental Paper mills-Amlai(M.P.)
ƒæ Mazgoan dock Ltd Mangalore ¡V Oil& gas platforms.
ƒæ Tata 500MW power project ¡VTrombay
Eductation
[1986 ] Technical Education Board Bangalore
Diploma engineering (chemical)With 4th rank
Certification
MS-Office 2003
Additional Information
14.12.06 to Till date Consolidated Contractors Company Saudi
SITE Engineer Piping
PROJECT : NGL Recovery Project
OWNER : Saudi Armco
PMC : JGC
Responsibilities and Nature of experience
Being Piping In Charge responsible for managing total Fabrication and Erection activities of Piping and reporting to Construction Manager and Site Manager. The Quantum of Piping work is 9, 50,000¡¨ dia of Fabrication and 1, 60,000¡¨dia of Piping Erection of Carbon Steel, Stainless Steel and Alloy Steel. I am controlling a team having strength of around 335 Nos include Engineers, Foremen- 12 Nos and work men ¡V 350 approx, responsible for complete piping activities in train 2 and surge product area, such as test packs, consulting engineering problems, arranging the material tools, planning for erection works preparation of daily progress reports etc.
12.06.05 to 04.06.2006 Consolidated Contractors Company Oman
Site Engineer
PROJECT : Sohar Refinery Oman
OWNER : Sohar Refinery Oman
PMC : JGC Japan
Responsibilities and Nature of experience
Being Piping In Charge responsible for managing total Fabrication and Erection activities of Piping and reporting to Construction Manager and Site Manager. The Quantum of Piping work is 8, 00,000¡¨ dia of Fabrication and 2, 15,000¡¨dia of Piping Erection.