Career Objective
A result-oriented professional with 05 Years experience in Project and O&M(Control & Instrumentation)
Professional Experience
Present organisation
Lanco Anpara power Limited, Anpara (U.P.) as Asst. Executive (C&I), since Jan 2012.
Company profile – A sub division of Lanco Infratech Ltd is one of India’s top business conglomerates and among the fastest growing. Lanco Infratech has subsidiaries and divisions across a synergistic span of verticals. These include Construction, Power, EPC, Infrastructure, Property Development, and Renewable. Lanco has operational and under execution projects amounting to over 11070MW.
Plant Detail - M/s LANCO POWER, ANPARA, SONEBHADRA (U.P.)
Plant Pattern: 2X600 MW Thermal Power Plant with Sub critical wall firing pulverized coal boilers of
2200 TPH each.
Previous Organisation
Instrumentation Limited,Kota as Contract Engineer(C&I),Since Dec 2009 To Dec 2011
Company profile-‘Instrumentation Ltd.’ is a Government of India Enterprise set up in 1964 with the prime objective of attaining self reliance in the field of Control and Automation for process industry. With over forty years of experience IL has mastered all complexities of control system, testing, system integration, installation, final commissioning to after sales services.
Plant Detail – M/S UPRVUNL, HARDUAGANJ, ALIGARH (U.P.)
Plant Pattern: 2x250MW, 1x110MW, 6x60MW Thermal Power Plant with tangential firing pulverized coal boilers of BHEL.
Previous Organisation
Process Instrumentation Works as Engineer(C&I),Since July 2008 To Nov 2009
Plant Detail – M/S UPRVUNL, HARDUAGANJ, ALIGARH (U.P.)
Plant Pattern: 2x250MW, 1x110MW, 6x60MW Thermal Power Plant with tangential firing pulverized coal boilers of BHEL.
Eductation
• B.Tech. in Electronics & Instrumentation Engineering from Northern India Engineering College (U.P.) with 64.36% in 2008.
• Passed out XII from A.M.U with 57% in 2003.
• Passed out X from A.M.U. with 79% in 2001.
Additional Information
INVOLVEMENT IN PROJECT.
• Successfully commissioned and synchronization of Unit I & Unit II of 600MW at Lanco Anpara Power Ltd.
• Successfully commissioned and synchronization of 110 MW Unit and 2x60 MW at Harduaganj Thermal power station under Instrumentation Limited kota.
• Erection planning / supervision at Boiler area.
• Involve in installation & commissioning of ACTUATORS (AUMA MATIC, AUMATIC, AUMA INDIA E-PAC, ROTORK IQTM SERIES, ROTORK AWT, ROTORK A RANGE, ROTORK JORDAN, SIPOS ECOTRON, SIPOS PROFITRON, ILK SERIES, CHINESE ACTUATORS etc).
• Involve in installation & commissioning of Control valves (ABB, Fisher, Forbes Marshall, Siemens,SMC).
• Involve in installation & commissioning Mill system & instruments. Gravimetric feeder Calibration.
• Responsible for erection & commissioning of Ignition control system, electrode type Drum level indicator, Oxygen Analysis System.
• Fully responsible for commissioning of Burner flame scanner for LDO, HFO & COAL.
• Fully participate in commissioning of PA Fan, ID fan & FD Fan.
• Responsible for commissioning of soot blower system
• Work in Foxboro DCS system for testing, commissioning and logic checking.
Co-ordination with vendors & EPC group for proper functioning of project execution.
• Monitoring & execution of Project activities to complete within schedule time.