| Reference | LT10104700 |
| Date | 5/16/2010 |
| Location | Middle East |
| Scope | 24" crude oil pipeline from Dukhan to Mesaieed tank farm dent repair by one of two options " Repair the Large Indentation from the vehicle impact by cutting 22 meters and replacing of the dent area with one of two options: - Option # 1: TDW or equivalent plugging system using two fittings and product temporarily stopped and finally using TDW or equivalent Lock-O-Ring Plug. The flow interruption shall not exceed fourteen calendar days. - Option # 2 (Alternative): 1- No interruption of crude oil flow in the pipeline by TDW or equivalent double stopple line procedure using four hot tapping fittings and a bypass and finally TDW or equivalent Lock-O-Ring Plug. 2- Repair Damaged Pipe retainers. 3- Repaint the repaired area according to the company specification # QP-SPC-L-002 Schedule 2U. |
| Bid Bond | QAR 50,000 |
| Bond Validity | 150 days |
| Offer Validity | 120 days |
| Documents Price | QAR 200 |