| Reference | 58.10.4079 |
| Date | 8/14/2010 |
| Location | Middle East |
| Scope | Two complete skid mounted verification provers units for calibrating the metering skids for custody transfer high - tech multi beam ultrasonic flow meter under actual process conditions for custody transfer metering system which are installed in Oziar Intermediate Station and the new company’s refinery. |
| Bid Bond | 1% of the contract price |
| Bond Validity | 120 days |
| Offer Validity | 120 days |
| Documents Price | USD 600 |