Dehydration and Desalting Unit
Gas dehydration
Reference PRJ.10.4081
Date 8/15/2010
Location Middle East
Scope Noor oil field is one of important crude oil fields within the company responsibility. It is located at about 10km northeast Amara city. This field is partially developed & the existing production facilities (degassing station – one bank) (40000 bopd) design capacity. The company intends to develop this field up to production rate of 40000 bopd during the next two years, due to expected wet crude oil produced later on. The company intends to install a new dehydration & desalting unit to treat crude oil with a capacity of 40000 bopd, including & not limited to:

- Two indirect water bath heaters, each heater with capacity of 40000(bopd).
- Complete dehydrator, with top mounting degasser with all accessories.
- Complete desalter with top mounting degasser with all accessories.
- Process equipment electrical system including PMCCS inters connecting cabling and accessories.
- Complete package of control system local and remote.
- Interconnecting piping sys. Including valves & fittings and accessories.
- Process pumps such as fresh water pumps (2*100%) & recycle pump (2*100%).
- A complete effluent water treatment system friendly environment type taking into consideration that the plant located at water flooded area drained to Water River & marsh. The unit should be contained two skimmed oil pumps & two effluent water pumps & filtering system to get clear water to be drained to a decantation pit.
- A complete set of drainage system, with a suitable pump with all accessories.
- A complete sets of chemical system (demulsifier & anti corrosion system & anti foaming system)

The scope of work required covering design, engineering details, procurement of equipment and materials, delivery of equipment and materials. The unit shall be designed for 40000-bbl/d dry crude basis. Vessels prefabrication shall be carried outside the country.

Scope of work also include details of design vessels fabrication drawings and hook up drawing, ISO metrics drawing, construction and commissioning procedures, . etc. It shall include performance guarantees and equipment / materials guarantee for 12 months after provisional acceptance.

Bidding Information

Bid Bond 1% of the contract price
Bond Validity 120 days
Offer Validity 120 days
Documents Price USD 100
Gas dehydration
Related Prooducts: Gas dehydration Gas dehydration Gas sweetening Gas Treating General GTL Processing LNG Processing LPG Domestic use LPG Odorless Packing Phase Separation Scrubbers
Related Tenders: Gas dehydration Gas sweetening Gas Treating General LNG Processing LPG Domestic use Packing Phase Separation Scrubbers

Related Articles

For Buyers
Advertise your Purchasing Requests

For Suppliers
Promote your Products
Egypt Zones
Copyright © Universal Solutions All rights reserved. - Privacy Policy.