Reference | 9-2011 |
Date | 1/15/2012 |
Location | Middle East |
Scope | The project will cover the following: design, supply, erection and operating steam boiler, the project (on turn key job basis). The project will be delivered to HRC in guaranteed conditions workings. The boiler should be prefabricated and can be put together in on year , at most, according to the following technical specifications : - Outlet steam pressure: 38 kg/ cm². -Outlet steam temperature: 450±5 C°. - Outlet steam quantity: 25 t/h at least. - Number of the burners: according to design / preferred with two burners. |
Bid Bond | Euro 72,000.00 |