Reference | GT12112100 |
Date | 9/16/2012 |
Location | Middle East |
Scope | The scope of work covers the FEED for the replacement of the existing 30-Inch ONSAG Pipeline from Station B to Station S, which in summary entails the: 1). Provision of a new pipeline with the associated block valve stations, pigging, flow metering, telecommunication, power and other required facilities. 2). Provision of leak detection, corrosion protection, fire/gas detection and fire protection systems. 3). Provision of all operating, control and safeguarding systems required for the optimal and safe operation of the new pipeline. 4). Decommissioning, demolition and writing off the replaced section of the existing 30-Inch ONSAG pipeline. |
Bid Bond | QAR 200,000.00 |
Bond Validity | 150 days |
Offer Validity | 120 days |
Documents Price | QAR 500.00 |