Location | Africa |
Scope | The successful contractor will undertake procurement and supply to site all materials, construction and commissioning of the following work components:- i. Cross country pipeline construction works including all associated civil, mechanical and corrosion control works. ii. Tie-in works of the new pipeline to the existing stations including associated mechanical, electrical, civil, corrosion control, instrumentation & control and communication system works. iii. Fibre optic cable installation along the entire pipeline route and associated terminal equipment at the stations. iv. Upgrading of fire detection and firefighting facilities in the stations. v. Quality Assurance tests for the entire works during construction, precommissioning, commissioning and start up works at completion. vi. Maintenance of the system during defects liability period including attending to defects. |