Reference | 2534-10-304 |
Date | 1/18/2011 |
Location | Middle East |
Scope | Ugradation of SBU & SGU control system. Job includes carrying out basic and detailed engineering, preparation of BOM, procurement of equipment / materials, shipping, preparation of BOQ, construction, inspection and testing, pre-commissioning, commissioning to upgrade the present non redundant control system into a dual redundant configuration for the existing Siemens S7-300 Programmable Logic Controller (PLC) at the Sulfur Bagging Unit (SBU) of Sohar Refinery. Vendor shall provide all the required services to carry out the project on EPC basis. |