Scope |
The works comprise the construction and commissioning of a new 11 kV elevated substation with a capacity of 12 MVA in Ahmadi area, comprising a new 15 kA 11 kV switchboard with associated control panels, data acquisition panels, battery and battery chargers, substation transformers and all installations as described in the Contract.
The works shall also include, but are not limited to, review of the Company provided Drawings and preparation of construction working Drawings and as-built Drawings, provision of materials and all necessary labour, plant and equipment, and any and all works which could be reasonably deemed necessary and as described in the Contract to complete the works.
|