Scope |
EPIC for Telemetry Upgrade & Replacement project at PS-2 & PS-3. To replace/upgrade the existing telemetry system on wellhead jackets & Production Station with a latest & proven technology based telemetry system complete with their radio communication to res pective Production Stations in MM and BH fields which can improve maintenance efficiency, provide flexibility in engineering & configuration, provide advanced operator functions and create an integrated centralized operational environment by a seamless & direct interface with existing Yokogawa DCS (CS 3000 R3.08) on production stations.
To Interface the existing DCS at Production Stations PS2 & PS-3 with existing onshore (QP ICT Data Centers) located OSIsoft PI historian servers thru their modification for real-time data transfer from offshore wellhead facilities and test separators to end user's offices in and around Doha via existing QP ICT network. |