Reference | GT14112000 |
Date | 9/14/2014 |
Location | Middle East |
Scope | Contractor shall complete the remaining uncompleted following works on EPIC basis at various stations within Dukhan Fields: a. Reinforced concrete pre-cast wall at PWI-S5/Diyab Manifold. b. Shelters for Nitrogen tankers at RG plant (Arab D Station). c. Car parking shelter at PWI-S1d. d. Chemical stores at Khuff A,B,C,D,E,G,H and L. e. Recovered oil sum pit at FMDGS. f. Closed drain pits and catchment pit at KNDGS, KMDGS, KSDGS, Jaleha and FSP. g. Access/maintenance road at PWI-S5/Diyab manifold. h. Access road for RG plant (Arab D), FMDGS and PWI-S1. i. Interlock paving tiles at PWI-S1 and NFCIS. j. All associated electrical, mechanical and instrumentation works. |
Bid Bond | QAR 250,000.00 |
Bond Validity | 150 days |
Offer Validity | 120 days |
Documents Price | QAR 500.00 |