Reference | LT15102700 |
Date | 4/16/2015 |
Location | Middle East |
Scope | The scope includes complete demolition of the existing Dukhan Power Station including all buildings structures, Plant equipment, gas turbine units, chimney stacks, transformers, diesel tanks, oil coolers, pipe lines, electric cables, underground pipes, drain pits, fire & gas system, fire hydrants, A/C equipment, SCS and PMS equipment, work stations, fibre optic cables and all other existing utilities. |
Bid Bond | QAR 150,000.00 |
Bond Validity | 150 days |
Offer Validity | 120 days |
Documents Price | QAR 200.00 |