Reference | LTC/C/VEN/2805/16 |
Date | 11/10/2016 |
Location | Middle East |
Scope | The company announces its need for EPICC for QG1, QG2 AND QG3&4 Wastewater Recycle and Reuse Project (QGW Project). Company intends to install new waste water treatment facilities at its existing QG1 LNG Plants in Ras Laffan, to provide an alternative waste water management solution to avoid disruption of LNG supply. The objective is to construct a separate unit which will recycle the waste water coming from QG1 MBR and the new AGR / SRU Units of the Plateau Maintenance Project. The scope includes the installation of a bio-sludge drying bed to treat the sludge received from QG1, QG2 and QG3&4 through a Dehydration Technology that guarantees 75% dry matter. |