Reference | 07/2019 |
Date | 3/12/2019 |
Location | Africa |
Scope | The company announces its need for replacement of (16’’) low pressure gas loop from STN (2) to STN(4). The work involves replacing and connecting the (7500) m of dia.16 inch line of the low pressure gas loop between station(4) and station (2) including the civil and mechanical works required for the completion of the projects, such as pipe assembly, trenching, welding, pipe laying, testing, pipe inspection, finish the installation of the pipe and its accessories according to the drawings. |
Bid Bond | LD 10,000.00 |
Offer Validity | 180 days |
Documents Price | LD 1,500.00 |