Reference | HFY-CON/F&C1049-1072 |
Date | 7/15/2019 |
Location | Middle East |
Scope | The company announces its need for Provision of Engineering, Procurment, Construction and Commissioning of CPF2 Power Plant Workshop and Office Project. The workshop and office mainly includes two areas which are workshop area and office area with steel frame structure. The total building area is about 2750m2. The scope of work shall include as follows: 1- The workshop area mainly consists Gas Turbine Generator (GTG) major inspection, mechanical, instrument and control, electrical working areas and sheds. The office area mainly includes office rooms, electrical, instrument, mechanic and tools rooms. Auxiliary system including fire-fighting, water supply and drainage, electrical, Heating Ventilation Air Conditioning (HAVC) and telecommunication systems will be built as well. 2- Detail engineering works; 3- Procurement of related equipment and materials; 4- Construction of facilities; 5- Commissioning with spare parts. |
Documents Price | US 100.00 |