Scope |
The company announces its need for EPCC Contractor shall perform geological investigation & topographical survey, detailed design, materials procurement, construction and installation, commissioning, , supply of two years operation spare parts , as-built document submission and one-year warranty. The main scope are as follows: CPF1 Gas Compression System Upgrade: Two (2) HP compressors, two (2) LP compressors and two (2) stabilized gas compressors to be added (items supplied by Company); One (1) condensate separator and two (2) condensate pumps to be added; Power supply (switchgears and VFDs etc.) & control & telecommunication system to be expanded. Some related utilities to be expanded. CPF2 Gas Compression System Upgrade: Add one (1) HP compressors, two (2) LP compressors and two (2) stabilized gas compressors (items supplied by Company); Add one (1) condensate separator and two (2) condensate pumps; Power supply (new east substation etc.).
|