Egypt Zones accountACCOUNT
37.37 KL Tanks for Crude Oil Storage with Submersed Heating Coils
Barrels & Containers
Reference SJI4441P21
Date 6/1/2020
Location Asia
Scope The company announces its need for 37.37 kls capacity,7500 mm X 2500 mm X 2150 mm rectangular crude oil storage tank out of 6 mm thick IS:226 M.S plates with roof suitably skid mounted with all welded on structure along with heating coils.

The tank should have the following:
a) Both inlet & outlet of the tank shall be extended to 12 inch by suitably supported spacer spools from tank wall and the openings shall be of flanged
end connection (as per ANSI B16.5).
b) A dip hatch of 3 inch dia with suitable opening / closing facility shall be
provided at the center of the rectangular manhole cover (tank top). An additional MS plate of size 8 inch x 8 inch x 6 mm shall be welded to the tank
bottom plate, where the dip bob will hit during dipping. A dip stick has to be
provided (made of steel) with a handle and properly calibrated as per the
depth/height of the tank.
c) Ladders with hand rails at appropriate locations(one outside the tank for
climbing on the tank and the other one inside the tank; ladders should not be
placed on the valaves.
d) The tanks shall be complete with API 600 x 150 class gate valves with
companion flanges and stud & bolts for inlet and outlet of the tanks. The
valves shall be supplied from any one of the following make:
M/s AIL, M/s L&T, M/s LACIER Industries
e) Proper calibration marking should be there on the outside of the tank.
f) A 3 inch vent to be provided at the top of the tank to allow the escape of
gas/vapour
g) Bidder has to design a suitable heating coil of size not smaller than 1 1/2"
across the breadth of the tank. The coil has to be of Sch 160 material or XXS.
The inlet of the coil has to be provided with a 2" size (600 class) IBR Valve
(Press Max: 90 kg/cm2, Temp: 300 deg C) with a reducer to connect to the
coil. A NON RETURN VALVE needs to be provided at the inlet. Also a valve
of 1 1/2" needs to be provided of 600 class at the outlet of the coil. All valves
and fittings have to be IBR approved. Also all welding job in the coil needs to
be undertaken by an IBR Approved welder.

Steam will be injected at around 90 kg/cm2 and at 300 DEG C. So all valves
and fittings along with coil should be able to withstand high pressure and
temperature.

Welding Procedure: All welding procedure should be followed as per standard
norms & done by certified welder in the tank. However all the weldings in the
coil have to be done by IBR welder only. All welding electrodes should be as
per IS: 814. There should be minimum 3(three) layers of welding & all welds
should be visually inspected / examined. The critical welds should be
subjected to radiography test, magnetic particle test and dye penetration test.

Necessary test certificate must be shown at the time of inspection & provided
along with dispatch documents.
2.0 Surface Preparation: After completion of all fabrication jobs, the surface
preparation should be carried as follows:
i. All welds should be made free of slag, slag inclusion, pinholes, spatters etc.
Scrapping & Wire brushing should be carried out on all steelworks after
removing all oil & grease deposit if any using approved degreasing agent &
solvent.
ii. Sand blast cleaning should be carried out in a controlled blasting shop &
not during inclement weather conditions.
iii. The air used during blast cleaning & after cleaning should be dry & free
from moisture & all oil contamination.
iv. All sand blast cleaned surfaces should be coated with the prescribed
primer within 4(four) hours of blasting.
v. The coil has to be tested at a pressure 1.5 times the design pressure and
certificate in this regard has to be provided. OIL may depute its person for
witnessing such test.

3.0 Painting:
i. 2(two) coats of inorganic zinc primer of 70-80 micron DFT should be applied
all over the tank, skid, ladder etc.
ii. 2(two) coats of Synthetic Enamel paint of 90-100 micron DFT of Grey
colour should be applied on the inner & outer tank wall surface, ladder,
connections etc.
iii. 2(two) coats of Synthetic Enamel paint of 90-100 micron DFT of Black
colour should be applied on the Skid of the tank.
iv. Synthetic Enamel paint should be of make Berger, ICI, Nerolac, Shalimar
etc.
v. SKID: Skid shall be painted with surface resistant high solids, high build,
fast drying, polyamide cured epoxy mastic coating designed to protect steel.

Bidding Information

Bid Bond INR 160,400.00
Offer Validity 120 days
Barrels & Containers
Related Prooducts: Barrels & Containers Barrels & Containers General Metal Pressure Vessels Metal Tanks Plastic Pressure Vessels Steel Plates Vessels Internals
Related Tenders: Barrels & Containers General Metal Pressure Vessels Metal Tanks Steel Plates Vessels Internals

Related Articles

For Buyers
Advertise your Purchasing Requests

For Suppliers
Promote your Products
Egypt Zones
Copyright © Universal Solutions All rights reserved. - Privacy Policy.