The company announces its need for Upgrade HLPH Substation & Associated Unit Equipment – Substation Building and Auxiliaries: Installation and Commissioning of the Main Electrical Equipment Package.
Scope includes Engineering Procurement construction and Commissioning of Blast Proof substation Building HVAC, F G, Small Power & Lighting Cable Routing to the Remote Loads and Substation Ancillaries as well as installation, Testing and Commissioning of the free Issued Equipment such as 4 Off 2 4KV Switchgears 3 off 480V MCCS DC Charger and Batteries 2 off HV Transformers and NERS 1 off HV Motors 1 off Edgs and its associated master control panel fuel tank power control and instrument cables. |