Scope |
The company announces its need for Engineering, Procurement and Construction (“EPC”) for Associated Gas Compression Project Phase Seven (7). The company is undertaking a field development project to increase oil and associated gas production in the Bahrain Oil Field. As a result of this program, the associated gas production is projected to increase to volumes that need to be accommodated by the associated gas handling network. In order to accomplish this, expansion of the existing associated gas handling network by means of additional compression is required to further advance Tatweer Petroleum’s field development objectives. Therefore, the Associated Gas Compression Phase 7 project aims to install three (3) new compression stations to increase the field’s total compression capacity and for enhanced oil recovery purposes. The Scope of Work incudes Design, Procurement, Fabrication, Installation, Testing, Pre-Commissioning, Commissioning, and Start-Up of Three (3) Compression Stations CS12, CS13, & CS14.
|