Scope |
The company invites all prospective suppliers and contractors for EPIC for Upgrade of Mark VI Control Systems for AEG at PS2&3. Contractor shall provide the expertise, materials, specialized labour, supervision, test equipment, tools, software, hardware, documents, drawings and each and every item of expense necessary to carry out the WORKSITE survey, engineering design, procurement, assembly, Pre-FAT, FAT, delivery, installation, pre-commissioning, SAT, commissioning, start-up, seventy two (72) hour performance test and handover of the FACILITY for the performance of Upgrade of AEG Gas Turbine / DEMAG compressor control systems at PS-2 and PS-3. Contract Duration shall be eighteen (18) calendar months.
|